- Project name: New Industrial Establishment   

- Country: Mirandola (Italy)  

- Client: BIOPSYBELL SRL  

- Head of commission: Mirco Pellacani

- Estimated value of the contract: € 550.000,00   

- Work duration: 210 days  

- Work date beginning: March 2015

- Work date end: September 2015

 

Finance

- Order down payment 20% - beginning of work 30% - SAL 40% - validation 10%

- Bank bonds for the down payments that have a 4 month validity

- Verify costs

- Verify supply timing  

- Determine suppliers for emission of order and subcontracts

 

Production

Production times will be defined subsequently.

 

Set up

Beginning of the work before March with the company Prandini for the fireproof line.

We will issue a detailed work program subsequently.

 

Logistics

Daily deliveries on our behalf are forecasted.

The material that is necessary for the clean room will remain in our factory.